Spring 2019 – Demolition Phase

Full scale demolition began in mid-January and will run through mid-March depending on weather conditions.  Virtually all components of the existing buildings are being recycled. Wood joists and wood beams may be repurposed to make furniture and interior finish materials, all used metal will be recycled and concrete/masonry will be ground up and used for fill material.  Demolition has progressed smoothly, except for a few icy days when they did not want trucks hauling materials on the road.

Once the demolition is complete there will be some analysis of the existing soil conditions to determine what level of remediation must be done to the site to make it suitable to build on.  Once the analysis is complete and the site backfilled, it will be ready for the construction phase to begin.